Earned Value Management

EVM 10:00

Overview

What Is this chapter about?

Earned Value Management integrates the assessment of current results, deadlines, and costs. Based on the current status of task implementation (value generated), the time and cost required to achieve the objective are assessed. This enables early action to ensure delivery on time and within budget.

To whom is this chapter primarily addressed?

In small projects, the project manager monitors progress, determines earned value, and develops corrective measures. In larger projects, this responsibility is typically assigned to a project controller or a project management office.

What is the significance of the process discussed in the chapter?

Early and continuous monitoring of progress using earned value, combined with deadline projections, enables timely identification of problems and corrective action. This ensures a constant focus on the project goal and supports meeting the sponsor’s requirements and expectations.

How does the process work in practice?

The first step is to assess what has been achieved within a given period and with what level of effort. Actual results are compared with planned results. Trend analysis of reliable intermediate results supports deadline assessment. Cost and liquidity control enable evaluation of the project’s further course and corrective action.

What are the main challenges?

Calculating generated value and forecasting its development is difficult. Optimistic assessments should be replaced by conservative estimates. Payment plans and actual expenditures often diverge—continuous monitoring and double-entry bookkeeping are essential.

What are the key success factors in this process?

Honest assessment of actual results and accurate financial reporting are essential for evaluating progress and forecasting outcomes. The project manager’s judgement is critical when selecting corrective measures to achieve the project goal.

Goal

The objective of Earned Value Management is to measure project progress to achieve the objectives defined in 07:00 Planning & Scheduling (P&S), while taking unplanned events into account.

Deviations from the plan that exceed minor adjustments trigger further steps in the 14:00 Change Management (CM) and/or 12:00 Problem Solving Management (PSM) processes.

EVM reports enable the project manager and the project team to identify deviations from planned performance within a given period, monitor project progress, and forecast further developments, including deadlines and costs. This information may also be made available to other project stakeholders, enabling them to plan project-related activities more effectively.

Process

As part of this process -the current status of the project is first determined in order to forecast its further course. Once deviations are identified,corrective actions are initiated to minimise risk and increase the likelihood ofachieving the project objectives.

Earned Value Management diagram

Lecture notes

Further Readings

Andonov, S. (2016). Quality-I is safety-II: The integration of management systems. CRC Press.

Austin, R. D. (2021). Project management simulation: Scope, resources, schedule (Version 3). Harvard Business Publishing. https://hbsp.harvard.edu/product/7701-HTM-ENG

Aven, T. (2024). Risk assessment and decision making. Risk Analysis.

Barafort, B., O’Connor, R. V., Poth, A., & Messnarz, R. (Eds.). (2014). Systems, software and services process improvement (EuroSPI 2014). Springer.

BigBear.ai. (2025). ProModel: Advanced simulation and predictive analytics. bigbear.ai

Cadle, J., & Yeates, D. (2008). Project management for information systems (5th ed.). Pearson/ Prentice Hall.

Chandrasekaran, A. (2010). Attaining nirvana through EVM: The eternal mantra for managing projects effectively. In PMI Global Congress 2010—Asia Pacific Proceedings. Project Management Institute.

Chapman, C., & Ward, S. (2020). Managing risk in projects. Wiley.

Chattopadhyay, A. (Ed.). (2024). Handbook of computer architecture. Springer Nature.

Cesim. (2025). Cesim Project: Project management simulation. cesim.com

Dalluege, C. A., Wells, S. J., & Wells, G. (Eds.). (2024). Navigating an EU research project: Managing challenges to deliver success. Springer Nature.

Dechange, A. (2024). Projektmanagement—schnell erfasst. Springer.

EIA. (2025). Earned value management systems (ANSI/EIA-748). Electronic Industries Alliance. https://www.sae.org/standards/content/eia748e/

Federal Chancellery of the Federal Administration. (2025). List of key projects. admin.ch

Felske, P. (2003). Integrated project management. In Project management expert (Vol. 2). Rationalisation Board of the German Economy.

Gharajedaghi, J., & Ackoff, R. L. (1985). Towards systemic education of system scientists. Systems Research, 2, 21–27.

Hansen, H. R., Mendling, J., & Neumann, G. (2019). Wirtschaftsinformatik: Grundlagen und Anwendungen. De Gruyter.

Harder, C. (2021). Specialist in office and project organisation: Reference book. BoD.

HERMES. (2026). Hermes project management methodology. Swiss Federal Chancellery. admin.ch

Hofmann, A. (2022). The ten commandments of risk leadership. Springer.

Hüsselmann, C., & Hergenröder, J. (2024). Integrated earned value analysis. UVK Verlag.

International Function Points Users Group. (2026). IFPUG Standards. IFPUG Standards-IFPUG-International Function Points Users Group. https://ifpug.org/ifpug-standards

ISB. (2020). P038—Reporting on the Federal Government’s key ICT projects. Swiss Federal Chancellery.

ISO. (2012). ISO 21500: Guidance on project management. ISO.

ISO. (2020). ISO 21502: Project, programme and portfolio management—Guidance on project management. ISO.

ISO. (2018/2025). ISO 21508: Earned value management in project and programme management. ISO.

ISO. (2024/2025). ISO 21512: Earned value management implementation guidance. ISO.

Jeges, R. (2025). Project scheduling: Earned value analysis. jeges.id.au

Kahlbrandt, B. (2001). Software engineering with the unified processing language. Springer.

Khatib, M., Alhosani, A., Alhosani, I., Matrooshi, O., & Salami, M. (2022). Simulation in project and programme management. American Journal of Industrial and Business Management, 12, 731–749.

Kumar, S., & Dingh, P. K. (2025). Quantitative techniques for managers. Thakur Publication.

Lent, B. (2009). Analysis of selected strategies in multidimensional optimisation of project management processes. In SiTI’2009 Proceedings. Polish Knowledge Management Association.

Lent, B. (2025). Agile has failed. What’s next? Keynote, SSEME 2025, Ordos, China.

Levy, F. (2021). Decision making under deep uncertainty. Journal of Decision Systems.

Lewis, J. P. (2011). Project planning, scheduling & control (5th ed.). McGraw-Hill.

Liebowitz, J. (Ed.). (2019). The handbook of applied expert systems. CRC Press.

Liggesmeyer, P. (2009). Software quality (2nd ed.). Spektrum Akademischer Verlag.

Lock, D. (2020). Project management. Routledge.

Lukas, J. A.. (2026). How to make earned value work on your project, PMI Learning Library. https://www.pmi.org/learning/library/make-earned-value-work-project-6001.

Manglik, R. (2024). Business mathematics and operations research. EduGorilla.

March, J. G., & Shapira, Z. (2022). Organizational perspectives on risk and decision making. Decision Analysis.

Meredith, J. R., & Shafer, S. M. (2024). Project management in practice. Wiley.

Merziger, G., Holz, M., Timmann, S., & Wille, D. (2024). Repetitorium elementare Mathematik 2. Hanser.

Motzel, E. (2003). Performance evaluation and project progress. In Project management specialist (Vol. 2). Rationalisation Board of the German Industry.

National Defence Industrial Association. (2018). Earned value management systems intent guide (EIA-748-D).

Nielsen, K. (2021). Agile portfolio management. Taylor & Francis.

OSP. PMP Exam Formulas Assessment, 2013. (2026). libsyn.com u7hivS6JR0ZMum0z-zIrgmoxIoRV8-gozsZD4i8NF~24m39P9pPRmcKoHZeOtwkQJL3SL2I4WYBIe0Zxa5dUw4s0bGRi46eIS~tdAj5x62s-gwIMesA2zzbczqD3VeGjm7iQkMchqw&Key-Pair-Id=K1YS7LZGUP96OI.

Ottmann, R. (2003). Quality management. In Project management expert (Vol. 2). Rationalisation Board of the German Economy.

Special Projects Office Bureau of Naval Weapons, Department of the Navy (1958) PERT Summary Report Phase 1, Department of the Navy, Washington, DC, USA

Philips, J. (2010). IT project management (3rd ed.). McGraw-Hill.

Raydugin, Y. G. (2020). Modern risk quantification in complex projects. Oxford University Press.

Rechnitzer, T. (2022). Applying reflective equilibrium. Springer.

Santana, C., Loeneo, F., Vasconcelos, A., & Gusmao, C. (2013). Using function points in agile projects. Wordpress.

Schutz und Sulaiman. (2013). Projektkostenschätzung: Kostenermittlung in frühen Phasen von technischen Auftragsprojekten. Deutschland: Gabler Verlag.

Seligman, E., Schubert, T., & Kumar, M. V. A. K. (2023). Formal verification. Morgan Kaufmann.

Shinde, G., Srivastava, N., & Poojari, S. (2024). Project management. Thakur Publication.

SimulTrain. (2025). The training simulator. STS Sauter Training & Simulation. http://www.sts.ch

SPL. (2025). SimProject. simulationpl.com

Sterman, J., & Gozluklu, B. (2025). Project management simulation. MIT Sloan. mit.edu

Subhash, G., Zimmerman, G., & Ridgeway, S. (2022). Mechanics of materials laboratory course. Springer.

Sulaiman, T., Barton, B., Blackburn, T., (2006). Agile EVM-Earned Value Management in Scrum Projects, Proceedings Agile 2006 Conference, IEEE New York NY, USA.

Timinger, H. (2025). Modern project management. Wiley.

TopSim. (2025). TopSim business simulations. Tata Interactive Systems. https://www.topsim.com

Vanhoucke, M., & Vandevoorde, S. (2005). A simulation and evaluation of earned value metrics. Journal of the Operational Research Society, 58(10), 1203–1213.

Weaver, P. (2007). The origins of modern project management. In PMI College of Scheduling Conference Proceedings. Mosaic Project Services.

Wipp, M., & Richter, R. (2020). Indicator-based quality management. Vincentz.

🎼

Practice questions coming soon.